Completed Projects

Johannesburg Water Completed Projects listed below;

View the projects in picture at the end of the list

AssetAsset descriptionProject Manager AmountComments
1500895EI1305 - Aeroton Direct TowerJoseph28 956 736,4295% completion, planned completion is March 2020
1500860Construction of Lenesia PumpstationJoseph17 365 851,0999% completion, planned completion is March 2020
1501391S1405 - Thornifo Provision of Basic ServicesFaith 6 344 059,7798% completion, planned completion is March 2021
1500476BWW520 DF: Capacity increase Phase 2Peter Louw34 323 084,96completed
1501498CR1009 - Swiss HSE FacilitiesSajida Mia10 033 869,49completed
1501468S1304 - Lenasia Ext. 5 Wtr Ph2Tshilidzi Tshikovhi7 240 130,84completed
1501471S1304 - Lenasia Ext. 5 Wtr Ph5Tshilidzi Tshikovhi 7 630 235,63completed
1501472S1304 - Lenasia Ext. 5 Wtr Ph6Tshilidzi Tshikovhi6 493 932,69completed
1501474UR1301 - Paulshof Ext.1 Water PRPNthabiseng Seopela91 533,59completed
1501392UR1301 - WPRP Paulshof Ext.1John Gumbo/Tawanda/Joseph6 821 866,49completed
1501442UR1306 - Armadale Water PRPJohn Gumbo/Tawanda/Joseph 6 248 605,21completed
1501454UR1306 - Eastgate Water PRPLebea Rakobo8 315 331,65completed
1501466UR1306 - Gallo Manor Ext.3 Water PRPJohn Gumbo/Nthabiseng2 745 730,86completed
1501486UR1306 - Jukskei Ext 1 Wtr Ph1Brian Bokaba7 252 145,88completed
1501487UR1306 - Jukskei Ext 1 Wtr Ph2Brian Bokaba 4 927 809,45completed
1501488UR1306 - Klevehill Park Water PRPNthabiseng/Nhlanhla9 589 783,36completed
1501449UR1306 -Bryanston Ext. 34 Water PRPTawandira/Nthabiseng4 768 733,78completed
1501450UR1306 -Bryanston Mill Hill  Water PRPPolite/Nthabiseng 6 764 200,59completed
1501462UR1403 - Forest Town Wtr Ph3Brian Bokaba3 341 036,07completed
1501463UR1403 - Forest Town Wtr Ph4Brian Bokaba3 367 759,45completed
1501489UR1403 - Industria West Ph1John Gumbo / Nqobizitha Ndimande7 350 221,11completed
1501494UR1403 - Kengies AH Water PRP Phase 2Trevor Mbonan/ Polite2 996 644,79completed
1501440UR1404 - Dunkeld West Ph1Tshilidzi Tshikovhi/ Polite1 576 516,27completed
1501439UR1404 - Homestead Sewer PRPDibuseng2 139 775,60completed
1501437UR1404 - Strubensvalley Ph2Trevor Mbonani/Polite4 428 382,67completed
1501475UR1405 - Gold Reef Ophiton Water PRPJohn Gumbo/ Trevor5 017 639,99completed
1501477UR1405 - Gold Reef Springfield Water PRPJohn Gumbo/ Trevor5 489 492,16completed
1501478UR1405 - Hursthill Water Ph1Tawandira/ Trevor7 306 952,18completed
1501483UR1405 - Wemmer Water Ph1Tawandira/ Trevor4 743 216,62completed
1501484UR1405 - Wemmer Water Ph2Tawandira/ Trevor4 912 600,32completed
1501485UR1405 - Wemmer Water Ph3Tawandira/ Trevor5 607 898,18completed